FAST-41 permitting and US rare earth projects

FAST-41 is a federal program that sets a published timetable for every agency permit a major project needs and tracks it on a public dashboard. Title 41 of the Fixing America's Surface Transportation Act created it in 2015, and the Federal Permitting Improvement Steering Council runs it. Two rare earth projects tracked here are in it: Bear Lodge in Wyoming as a covered project and Sheep Creek in Montana as a transparency project.

FAST-41 is a process, not money. It sets dates and coordinates agencies, and it does not decide whether a permit is granted.

Verified through Oct 1, 2026

At a glance

Created by
Title 41 of the Fixing America's Surface Transportation Act (2015)
Run by
The Federal Permitting Improvement Steering Council (Permitting Council)
What it adds
A comprehensive permitting timetable and a public dashboard for each project
Two tiers
Covered projects, accepted into FAST-41, and transparency projects, posted on the dashboard at the Executive Director's direction
Not included
Funding, a guaranteed permit, state and local approvals
Critical mineral project covered
54thBear Lodge, Mar 20, 2026
Rare earth projects tracked here
2Bear Lodge (covered), Sheep Creek (transparency)
Bear Lodge timetable ends
Mar 2028Forest Service lists a decision in Jul 2028
Sheep Creek decision estimated
Jul 2027Forest Service estimate

What is FAST-41?

FAST-41 is a federal permitting program created by Title 41 of the Fixing America's Surface Transportation Act in 2015. The Federal Permitting Improvement Steering Council sets a timetable for each federal permit a qualifying project needs and tracks it on the public Federal Permitting Dashboard.

The Permitting Council is made up of its executive director, 13 federal agency members and the chairs of the Council on Environmental Quality and the Office of Management and Budget. It coordinates reviews, while a lead agency handles the project: the Forest Service for a rare earth mine on National Forest land, as at Bear Lodge.

Since 2025 the program has added many mining projects. The Council called Bear Lodge the 54th critical mineral and mining project to join FAST-41 when it announced the project on Mar 20, 2026.

What is the difference between a FAST-41 covered project and a transparency project?

A covered project is accepted into FAST-41 and entitled to a comprehensive permitting timetable managed on the dashboard. A transparency project is posted on the dashboard at the Executive Director's direction in the interest of transparency, with a scheduled timeline. Bear Lodge is covered, and Sheep Creek is a transparency project.

The two tiers of FAST-41, with the rare earth example for each
FeatureCovered projectTransparency project
How it gets thereThe project qualifies and is accepted as a covered project under Title 41.The Permitting Council's Executive Director directs it onto the dashboard.
What it getsA comprehensive permitting timetable and transparent, collaborative management of that timetable.A scheduled timeline posted on the Federal Permitting Dashboard.
Rare earth exampleBear Lodge, Wyoming, covered on Mar 20, 2026.Sheep Creek, Montana, added on Nov 19, 2025.

Which US rare earth projects are in FAST-41?

Two rare earth projects tracked in this directory are in FAST-41: Bear Lodge in Wyoming, a covered project since Mar 20, 2026, and Sheep Creek in Montana, a transparency project since Nov 19, 2025. Both are on National Forest land and both involve the Forest Service. The Dewey-Burdock uranium project in South Dakota was the first Black Hills mining proposal in the program.

US rare earth projects in FAST-41 and their federal dates, from the Permitting Council, the Forest Service and the directory profiles
ProjectTier and dateLead agency and sponsorFederal datesNotes
Bear LodgeCrook County, WyomingCovered projectMar 20, 2026Forest Service; sponsor Rare Element ResourcesPlan of operations submitted Mar 20, 2026. Scoping ran from late Jul to Aug 28, 2026. The FAST-41 timetable ends Mar 2028 (directory record); the Forest Service lists an estimated decision in Jul 2028; the company expects permitting to finish by early 2028.The 54th critical mineral and mining project in FAST-41. Radioactive materials licensing is separate: see NRC and Agreement State licensing.
Sheep CreekRavalli County, MontanaTransparency projectNov 19, 2025Forest Service; sponsor US Critical MaterialsForest Service estimates: scoping Aug 2026, decision Jul 2027, implementation Oct 2027.Gallium and rare earth exploration project. Ravalli County commissioners voted to ask the congressional delegation to remove it from the list, citing a lack of public engagement.

Both projects have their own profile with permits, public comment and community issues. The Permitting Council's other critical mineral projects, such as Nikolai Nickel in Alaska, are not rare earth projects.

How does FAST-41 change the timeline for a rare earth mine?

FAST-41 does not remove permits or environmental review. It sets target dates for each agency step, publishes them on a dashboard and gives the project a coordinated review. Press reports say the Permitting Council estimates it can cut about 18 months from a review, a figure this directory has not verified.

Bear Lodge on the FAST-41 timetable, from the directory profile and the Permitting Council
  1. Mar 20, 2026 Plan of operations submitted; project becomes covered Done Rare Element Resources files its mine plan of operations with the Black Hills National Forest the same day the Permitting Council announces FAST-41 coverage.
  2. Jul 29, 2026 Forest Service begins the review Done A 30-day public scoping period follows and runs to Aug 28, 2026. Under FAST-41 the review has no draft environmental impact statement or objection stage, according to press coverage, so scoping is a main chance to comment.
  3. Early 2028 Company expects federal and state permitting to finish Company Rare Element Resources' own expectation.
  4. Mar 2028 FAST-41 timetable ends Next The scheduled end of the Bull Hill plan of operations timetable, as recorded in this directory.
  5. Jul 2028 Forest Service estimated decision Next The date the Forest Service project page lists for a decision.

What does FAST-41 not do for a rare earth project?

FAST-41 does not fund a project, guarantee a permit or cover state and local approvals. It also does not replace the radioactive materials licensing that thorium-bearing rare earth ore can trigger. It is a federal process listing, so this directory counts it as support but not as money.

In Wyoming the state air, water and land permits and the radioactive materials license run beside the federal review. In Montana the state's Metal Mine Reclamation Act applies to Sheep Creek in addition to the Forest Service decision.

Coverage can also draw opposition. In Montana, county commissioners asked to drop Sheep Creek from the list, and residents cite water and fish in the Bitterroot headwaters. The Forest Service decides whether a project proceeds, and the dashboard only shows the schedule.

Which US projects, companies and states does this touch?

The pages below carry the figures, the sources and the dates for each project or company named here.

Questions about FAST-41 permitting

What is FAST-41?

FAST-41 is a federal permitting program created in 2015 by Title 41 of the FAST Act. The Permitting Council sets a timetable for each federal permit a qualifying project needs and publishes it on the Federal Permitting Dashboard.

Is Bear Lodge a FAST-41 project?

Yes. The Permitting Council announced Bear Lodge as a FAST-41 covered project on Mar 20, 2026, the 54th critical mineral and mining project in the program. The Forest Service is the lead agency and Rare Element Resources is the sponsor.

Is Sheep Creek a FAST-41 project?

Yes, as a transparency project since Nov 19, 2025. Its schedule is posted on the dashboard, with a Forest Service decision estimated for Jul 2027. Ravalli County commissioners asked to remove it from the list.

Does FAST-41 guarantee a permit?

No. It sets target dates and coordinates the agencies. The lead agency still decides, and state, local and radioactive materials approvals are separate.

Does FAST-41 give a project money?

No. It is a permitting process and not funding, so it is not counted in the totals of the government support tracker.

What is the difference between covered and transparency projects?

A covered project is accepted under Title 41 and gets a comprehensive timetable. A transparency project is directed onto the dashboard by the Executive Director in the interest of transparency, with a scheduled timeline.

Sources and verification

Each profile lists its sources, a confidence grade and a verification date. Order of authority: official records (SEC filings, agency documents), company documents and technical reports, research papers, then independent press. Syndicated copies and reference works are labeled and are never the only source for a number. Company-reported figures are labeled as such, and non-binding deals are labeled "letter of intent" or "conditional".

Tags show what kind of source each link is. How sources are ranked